ACM Direction for use-Preparation before commissioning

2017-04-18

Preparation before commissioning

1.1 If the power supply transformer is used to meet the total installed power of the equipment, the selection of the air compressor should be matched with the equipment. Specific installed power and air compressor requirements as shown in Table 1 .

Table 1. Installed power and air compressor requirements for each type

Type
Installed Power(KW)

Compressor Working Pressure(Mpa)

Displacement(m3/min)

Compressor Power(KW)
ACM42033
0.8/0.48
3

ACM700

700.8/0.48
5.5
ACM935
1300.8/17.5
1000A
205

0.8/2

15
HLM-880
1500.8/215
MT-1882100.8/215
FLM-11002600.8/215

1.2 Close the main power switch and check whether the three-phase voltage of the power supply is normal.

1.3 Open the air compressor, send air into the dedusting gas bag, checking the pulse valve, poppet valve working condition one by one (note, the pulse valve and the poppet valve the work order must correspond).

1.4 One by one to test the motor, check the direction of rotation if correct. From the cover to the motor direction:

Table 2 Each motor Steering

Type
Main MotorClassify Motor
ACM/Ring Roller MillAnticlockwiseClockwise

1.5 Check whether there is a foreign body in the electrical cabinet; whether the wiring is fastened; whether the manual transmission is flexible; check the pipe, the fastening screws of the connecting part of the body; the sealing of the pipeline.

1.6 Need to lubricate parts, whether the oil is sufficient.

Table 3. Place and time of filling grease

NoPlace of GreaseAdding MethodGrease NameTime Interval
1Speed ReducerChange in Repair Above L-CKD220 Heavy duty industrial closed gear oil3 months
2Crushing Shaft BearingPedal Lubricator3# Lithium base grease2 days
3Classify Shaft BearingGrease Gun3# Lithium base grease2days

4

Fan BearingChange in Repair 40# Machine oil 6 months
5Charging System Bearing Change in Repair 3# Lithium base grease6 months
6Discharge System BearingChange in Repair 3# Lithium base grease6 months
7Air CompressorChange in Repair 40# Machine oil 6 months

1.7 After running about a month time, need to conduct a comprehensive inspection of the equipment, found problems, timely troubleshooting.